Completed & Active Projects
Built. Documented. Inspected.
Every Reystone project follows the same discipline — plan, permit, build, inspect. Below are two representative projects showing our work from foundation through final.
Licensed General Contractor
Residential Addition
& Full Renovation
Residential expansion and full interior modernization.
1,200 SF second-story addition with ground-floor extension and complete interior renovation. Structural, framing, MEP coordination, kitchen, flooring, and finish work — executed under a single contract from foundation through final inspection.

Project Overview
The existing structure was a single-story residence requiring both additional living space and a full interior upgrade. The scope included constructing a second story, extending the ground-floor footprint, and renovating the entire interior — kitchen, bathrooms, flooring, and finishes throughout. All work was executed under a single contract with no scope subbed out. The project was permitted, inspected, and closed out through the local building department.
All phases were completed in sequence with required inspections signed off prior to proceeding to the next stage.
Scope of Work
What Was Built
Structural Work
Foundation reinforcement, new load-bearing walls, structural steel, and engineered connections to support the second-story addition.
Framing
Full second-story framing, ground-floor extension framing, roof structure, and exterior sheathing. All framing inspected and approved before close-in.
Kitchen Build
Complete kitchen demolition and rebuild. New layout, cabinetry, countertops, plumbing rough-in, electrical, and appliance installation.
Flooring
Existing flooring removed. New subfloor leveling, underlayment, and finish flooring installed throughout the entire ground floor and addition.
Interior Finishes
Drywall, tape, texture, and paint throughout. Trim, baseboards, door casing, and hardware. Bathroom tile, fixtures, and accessories.
Doors & Hardware
Interior and exterior doors — prehung units, hardware, and weatherstripping. All openings plumb, gapped to code, and operational at final inspection.
Field Conditions
What We Found. How We Solved It.
Existing Foundation Undersized
The original foundation was not designed to carry a second story. Load calculations required by the structural engineer exceeded what was in place.
Non-Standard Framing in Existing Walls
Existing wall framing did not follow standard spacing or blocking. Several load paths had to be re-engineered after demolition exposed the actual conditions.
Utility Relocation
Existing plumbing and electrical routing conflicted with the new floor plan. Both systems required partial rerouting before framing could proceed.
Material Lead Times & Supply Constraints
The project was executed during 2020, when material availability was limited and lead times extended significantly due to supply chain disruptions.
Foundation Reinforcement
Installed supplemental footings and steel connections per the structural engineer's revised plan. All work inspected and approved before framing started above.
Re-Engineered Load Paths
Worked with the structural engineer to redesign bearing connections based on actual field conditions. Added blocking, posts, and hardware where needed. No work proceeded without updated drawings.
Coordinated Re-Route
Plumbing and electrical rerouted in coordination with the new layout before framing was closed in. Rough inspections passed on the first call for all trades.
Procurement Planning & Sequencing Adjustments
Long-lead materials were identified and ordered during the planning phase. Work was sequenced around delivery timelines to maintain forward progress between phases.
Execution Details
By the Numbers
Executed under active supply chain constraints with no schedule breakdown between phases.
Documentation
Before, During, After



















Planning a similar project?
Active Project · South Gate, CA
Garage-to-ADU
Conversion
683 SF detached garage converted to a permitted 2BR/2BA accessory dwelling unit.
Full conversion scope — structural modifications, new foundation work where required, framing, MEP rough-in, insulation, drywall, and exterior stucco. All rough inspections passed. Final inspection pending.

Scope of Work
What Is Being Built
Structural & Foundation
Garage slab evaluation, new footings where required, structural modifications for residential occupancy load.
Framing & Rough-In
Wall framing for bedroom/bathroom layout, ceiling, MEP rough-in. All rough inspections passed.
Exterior
Stucco over new framing, integration with existing structure. Weather barrier and flashing per code.
Interior Finishes
Drywall, flooring, fixtures, paint, doors, and hardware. In progress — final inspection pending.
Execution Details
By the Numbers
Documentation
Progress Photos



Considering an ADU or garage conversion?
Portfolio
Same Process. Every Project.
Whether it's a second-story addition or a 683 SF ADU conversion, every Reystone project follows the same sequence: plan, permit, build, inspect. No phase starts until the previous one is documented and signed off.