Licensed General Contractor · Completed Project

Residential Addition
& Full Renovation

Residential expansion and full interior modernization.

1,200 SF second-story addition with ground-floor extension and complete interior renovation. Structural, framing, MEP coordination, kitchen, flooring, and finish work — executed under a single contract from foundation through final inspection.

Location Southern California
Scope Addition + Full Renovation
Addition Size ~1,200 SF
Role General Contractor (Self-Performed)
Year 2020
Completed two-story residential addition with stucco exterior, stone walkway, and landscaping — front elevation
Completed — front elevation, second-story addition

The existing structure was a single-story residence requiring both additional living space and a full interior upgrade. The scope included constructing a second story, extending the ground-floor footprint, and renovating the entire interior — kitchen, bathrooms, flooring, and finishes throughout. All work was executed under a single contract with no scope subbed out. The project was permitted, inspected, and closed out through the local building department.

All phases were completed in sequence with required inspections signed off prior to proceeding to the next stage.

What Was Built

01

Structural Work

Foundation reinforcement, new load-bearing walls, structural steel, and engineered connections to support the second-story addition.

02

Framing

Full second-story framing, ground-floor extension framing, roof structure, and exterior sheathing. All framing inspected and approved before close-in.

03

Kitchen Build

Complete kitchen demolition and rebuild. New layout, cabinetry, countertops, plumbing rough-in, electrical, and appliance installation.

04

Flooring

Existing flooring removed. New subfloor leveling, underlayment, and finish flooring installed throughout the entire ground floor and addition.

05

Interior Finishes

Drywall, tape, texture, and paint throughout. Trim, baseboards, door casing, and hardware. Bathroom tile, fixtures, and accessories.

06

Doors & Hardware

Interior and exterior doors — prehung units, hardware, and weatherstripping. All openings plumb, gapped to code, and operational at final inspection.

What We Found. How We Solved It.

◆ Challenges

Existing Foundation Undersized

The original foundation was not designed to carry a second story. Load calculations required by the structural engineer exceeded what was in place.

Non-Standard Framing in Existing Walls

Existing wall framing did not follow standard spacing or blocking. Several load paths had to be re-engineered after demolition exposed the actual conditions.

Utility Relocation

Existing plumbing and electrical routing conflicted with the new floor plan. Both systems required partial rerouting before framing could proceed.

Material Lead Times & Supply Constraints

The project was executed during 2020, when material availability was limited and lead times extended significantly due to supply chain disruptions.

◆ Solutions

Foundation Reinforcement

Installed supplemental footings and steel connections per the structural engineer's revised plan. All work inspected and approved before framing started above.

Re-Engineered Load Paths

Worked with the structural engineer to redesign bearing connections based on actual field conditions. Added blocking, posts, and hardware where needed. No work proceeded without updated drawings.

Coordinated Re-Route

Plumbing and electrical rerouted in coordination with the new layout before framing was closed in. Rough inspections passed on the first call for all trades.

Procurement Planning & Sequencing Adjustments

Long-lead materials were identified and ordered during the planning phase. Work was sequenced around delivery timelines to maintain forward progress between phases.

By the Numbers

~1,200 SF
Addition Size
2 Story
Structure Type
Mid 6-Figure
Project Value
Self-Performed
Crew & Execution
Permitted
All Inspections Passed

Executed under active supply chain constraints with no schedule breakdown between phases.

Before, During, After

Exterior — Front Elevation
Front elevation with second-story framing going up above original single-story structure
Framing
Front elevation with stucco finish coat being applied, crew on scaffolding
Stucco
Completed front elevation with stucco, landscaping, and stone walkway
Completed
Exterior — Rear Elevation
Rear elevation during framing — second-story addition with sheathing, crew on structure
Framing
Rear elevation during stucco application, full crew on scaffolding
Stucco
Completed rear elevation with stucco, windows, balcony, and second story
Completed
Structural & Interior Framing
Interior ceiling joists exposed with crew working on second-story floor framing
Ceiling Joist Framing
Front elevation during stucco and lath application, crew on scaffold and roof
Exterior Lath & Stucco
Kitchen — Before, During, After
Original kitchen with dated tile counters, terracotta floor, and outdated cabinets
Before
Kitchen during demolition — exposed framing, crew working, walls opened up
During Demo
Completed kitchen with white shaker cabinets, quartz island, hardwood floors, and stainless appliances
After
Bathroom — Before, During, After
Shower pan framed with raw plywood, plumbing rough-in visible, exposed studs
Before — Framing
Shower tile installation in progress — marble-look wall tile set, niche roughed in, floor unfinished
During — Tile
Completed bathroom with marble-look tile shower, glass enclosure, rain head, and mosaic floor
After

Approach

Structured Execution. Clean Closeout.

Every phase of this project followed the same process: plan, verify, build, inspect. No scope was skipped. No work was covered before it was documented. Every inspection was passed before the next phase started.

That approach doesn't change based on the size of the project. The same discipline applied here is built into every contract Reystone takes on — residential, commercial, or public works.

See what Reystone can do for your next project.

Request a Bid View Capabilities